Project Number: |
|
FDC-007-101794.1 |
|
Project Title: |
|
Demolish Greenhouse |
|
Location: |
|
Forest District 07, Bald Eagle State Forest, UNION COUNTY, HARTLEY |
|
Issue Date: |
|
6/9/2021 |
|
Due Date: |
|
7/8/2021 ( 2:00 PM ) |
|
Work Includes: |
|
Work included under this contract consists of the removal and disposal of Asbestos Containing Material (ACM); and the demolition, disposal, and backfill of the existing structures as indicated in the contract drawings and enclosed Exhibit A (Demolish Greenhouse). Work also includes abandonment of waterline and electric, grading, topsoil, and seeding.
Responsive bidders must hold a current small business certification from Pennsylvania
Department of General Services
Engineer's Estimate: $50,000 to $100,000 |
|
|
|
Request Bid Package
|
|
Addenda: |
|
|
|
Addendum Date: |
|
|
|
|
Click on the name of the Plan Holder in the list below to view detailed information.
|